 |
|
|
 |
Products > PSOP > Documentation
Compare Usage Profiles Tab
The top of the Compare Usage Profiles tab shows resource utilization and over-allocation for the PSOP schedule and the original P3e schedule.

The
height of the curve indicates the resource utilization for a given
time. For example, we can see that on a date about halfway between
November 25, 2003 and December 7, 2003, the original schedule required
a
bit more than 30 units. The green part of the curve indicates
resources that were available while the red part of the curve
indicates over-allocated resources. In other words, the height of the
red bar
indicates the amount of over-allocation.
The black line at the far right of the plots indicates when the
schedule completes. For some projects, there may be activities
at the end of the project that do not use any resources so there may be
a gap between the resource curves and the black finish line. The
black line indicates when all activities, with or without resources
assignments, have completed. In this case you can see that the
Primavera schedule completes on December 19, 2003 and the PSOP schedule
completes on December 2, 2003.
Below the curves are two selection boxes. The Resource
selection
box contains a list of all the resources used by the project. Selecting
one of the resources causes the plots to redraw so they
show utilization and over-allocation only for the selected resource.
Selecting a resource will also cause the summary table below the plots
to include a row with overload statistics for the selected resource.
Selecting "Cumulative" shows all resources combined.

In the above example, we see that resource LABORPY has been
selected. The plots now show utilization and over-allocation only for
this
resource. The black line indicates the availabilities for this
resource. Note that there is no availabilities line on
the cumulative resource plot as it would not make sense (more information...).
In this example, the availabilities go down for the 2nd shift of each day.
It is common for availabilities to fluctuate in conjunction with a
calendar. For example, often resources do not work on the
weekends. By choosing a calendar from the Calendars selection box you can cause the plots to show only those days and times that are working times in the selected calendar.
Selecting the Overload Only check-box
will cause the plot to show only the red portion of the curve. This can
be useful when there is a lot of work and only a little bit of
over-allocation. In such cases the over-allocation can be difficult to
see unless the rest of the work is hidden.
The plots can be zoomed by placing the mouse cursor over the horizontal
or vertical axes of either plot. To zoom horizontally place the mouse
cursor over the horizontal axes. The cursor will become a double-ended
arrow. If you click with the left mouse button and drag the mouse
horizontally you can zoom in to show only a subset of the dates.
Similarly, when the mouse cursor is over the vertical axes the cursor
will become a double-ended vertical arrow and you can zoom vertically
by clicking and dragging up or down.
The bottom of this tab contains a table comparing the schedules.

The Early Start Schedule refers to a schedule in which each activity
was scheduled as early as constraints and relationships would allow.
The early start schedule does not pay attention to resource
utilization or leveling. It is shown for comparison as it is
impossible to produce a schedule which finishes any earlier. For
the McDonnell Douglas Wing example, the Early Start Schedule has
1,828.77 hours of overload. The Original Schedule, which was produced
by the P3e leveler, has 148.95 hours of overload, and the PSOP schedule
has no overload. The amount of overload refers to the number of
resource hours scheduled in excess of the resource availability. The improvement column compares the PSOP
Schedule to the Original Schedule. It indicates that the PSOP
schedule saves 148.95 hours of overload and is 16.78 days shorter than
the Original Schedule. PSOP improvements are highlighted in yellow.
The duration row indicates how long each schedule required to complete
the project. We can see that the Original Schedule required 60.28 days
to construct the airplane wing while the PSOP schedule completes the
project in only 43.5 days; a savings of 16.78 days.
When a resource is selected in the Resource
selection box the table will show an additional row labeled "Resource
Overload". This will show how over-allocated the selected resource is
in each of the three schedules. The other two rows, labeled "Overload"
and "Duration", remain unchanged and indicate values for the entire
project.
|
|
 |
|