Why does PSOP say my requested finish date is impossible?
Activity
relationships, constraints, and durations affect the minimum possible
schedule length. For example, consider a project with two activities: Write FAQ and Publish FAQ with the obvious finish to start
relationship between the two. If writing the FAQ will take 10
days and publishing it will take 4 days, then the shortest possible
schedule is 14 days. If the project starts on January 1 and you ask
PSOP to create a schedule that finishes earlier than January 15, PSOP will warn that the requested finish date is
impossible.
In addition to relationships, Start on, start on or before, finish on, mandatory start, and mandatory finish constraints can also affect minimum schedule lengths.