 |
|
|
 |
Products > PSOP > Documentation
Why do my Level of Effort
activities have a longer duration than necessary?
If the project contains a WBS summary activity that summarizes an Level
of Effort (LOE) activity then the LOE activity will incorrectly have
the same start and end dates as the WBS activity. For example, suppose
you had three activities A1, A2, and A3 which are scheduled at the
following times:
| Activity |
Start Time |
End Time |
| A1 |
0 |
10 |
| A2 |
5 |
15 |
| A3 |
10 |
20 |
Furthermore, assume all three activity have WBS code W.1. We then add
an LOE activity with WBS code W.1 which has A1 as a predecessor and A2
as a successor. The LOE activity should thus start at time 0 (when A1
starts) and finish at time 15 (when A2 finishes). If we add a WBS
summary activity for WBS code W, our WBS activity will summarize A1,
A2, A3, and our LOE activity. The WBS activity thus starts at time 0
(the earliest start of any of the activities it summarizes) and
finishes at time 20 (the latest finish of any of the activities it
summarizes). In this case PSOP would incorrectly schedule the LOE
activity to have the same start and finish dates as the WBS activity
that summarizes it. The LOE activity would thus finish at time 20 instead of finishing at time 15.
This is a known bug that will be fixed in a future version.
Back to FAQ
|
|
 |
|