 |
|
|
 |
Products > PSOP > Documentation
Handling of In-Progress and Completed Successors
Generally a successor activity will not start before its predecessor.
It can happen, however. If it does, P3e ignores the relationship
if the successor is complete and keeps the relationship if the
successor has started but not finished.
By default PSOP will ignore relationships when the successor is complete and will ignore finish to start and start to start relationships when the successor has started but not finished. If you un-check ignore successor relationships to completed work option in the Primavera Compatability tab on the main window, PSOP will honor all relationships to started or finished successors.
For example, consider a project with two
tasks, Write
Manual and Publish Manual.
Since the manual must be written before it can be published, there is a finish to start relationship and Publish
Manual is a successor of Write Manual. Suppose that the Publish Manual task is somehow complete while the Write Manual task has not started; it is not clear how to handle the
relationship. As P3e allows a task that is
in the future to be started, it may still be possible to schedule the Write Manual activity such that the
relationship is honored. In PSOP, if the ignore
successor relationships to completed work option is un-checked in the Primavera Compatability tab on the main window, the relationship is honored if
possible. Furthermore, if it is not possible to honor the relationship,
PSOP will schedule the Write Manual
activity as soon as possible. If the ignore
successor relationship to in-progress work option is checked, PSOP will ignore the relationship and schedule the Write Manual activity at a time that
minimizes the total schedule over-allocation and duration.
Note that in some circumstances it may make sense for a successor to
start before its predecessor. For example, a project may have some
paperwork that must be done close to the end of the project, but does
not have to wait until the very end of the project. The Paperwork activity might then be a successor of the Last Task activity. There could be a finish to start constraint between the Last Task and Paperwork activities with a negative lag indicating that the paper work can begin before the last task is complete. In such a case the Paperwork might be in progress or finished before the Last Task had started.
We recommend leaving the ignore successor relationships to completed work
box checked. If the successor was able to complete it generally means
that the constraint was satisfied in practice and it thus does not
matter when the predecessor starts.
|
|
 |
|