PSOP is designed to improve upon the leveling technology in P3e. Its advantages include:
- Better schedules: This is the big one! PSOP produces shorter schedules with less overload. Example and details
- Leveling by role: While P3e
allows you to assign resources or roles to activities, it will only
consider resources when leveling. PSOP allows you to level using
resources, roles, or a combination of both. PSOP can even substitute
primary roles for resources that have already been assigned. Example and details
- Splitting in-progress tasks:
If a task is partially complete, the P3e leveler might separate the
remaining work from the completed work. In many cases, this does
not makes sense - once a task has started, you do not want it
interrupted. The is no
way to prevent P3e from doing this, short of adding constraints or
mandatory dates to the in-progress activities. PSOP does not
split in-progress tasks unless requested to do so. Example
and details
- Honoring
constraints: Primavera P3e ignores finish on or before and start on or before
constraints when not leveling within total float. PSOP will
honor these constraints unless instructed to ignore them. Example and details
- Handling
unavoidable overload: If a task cannot be placed in a
position that
eliminates all of its overload, the P3e leveler will place the task at its early
start. PSOP will instead place the task at the position that minimizes its overload. Example and details
- Correct handling of resource calendars:
The P3e leveler does not correctly handle resource calendars and may schedule activities to work when the resources
needed are not available. PSOP handles resource calendars correctly. Example and details
|
|
 |
|